June 2007
Beautification Committee Forms
August 2007
Estimate of $100,000 for Restoration of the Original Graveraet Fountains and Courtyard made
Information Packets about the restoration project given to MAPS Board of Education members and Administrators
September 2007
Finance Committee Meeting on scope of Beautification Project
Approval has been given by MAPS Administration to start the Beautification Project
The Kaufman Endowment Fund Board Promises a 2-1 match up to $50,000
October 2007
Fall Kick –off Ceremony in the Graveraet School Courtyard
November 2007 - May 2009
Development of Major Gifts from community members and local businesses
May 2009
Bid process for labor of the project
June 2009
Award labor contracts
August 2009
Fundraising for major gifts ends
Break ground for the new fountains and courtyard
All donations requiring stone engraving due in full
September 2009
Restored Graveraet Courtyard and Fountains/Ohio Street Project completed